A building process is the beginning of a journey to something new and exciting. Take a step on that journey by calling Keystone today.

The first step is to establish a partnership with you. Understanding the goals for your building project and agreeing how we can work together to achieve those goals.

Our Process

No two building projects are the same and the timelines can differ dramatically depending on the size and complexity of the project.

However, as a guide, below we have set out a process that we typically follow.

  • 1

    Discovery

    Our partnership really begins at the discovery phase.

    - Establishing the goals for your building project
    - Understanding what a successful outcome will be
    - Agreeing the potential options that are available
    - Mapping the journey
    - Agreeing the timeline

  • 2

    Design

    Design builds on discovery by moving from ideas and objectives to concrete plans. You may or may not have plans and approval for your project, either way design is where inspiration and imagination come together to help you visualise what you want your home to look and feel like once the project is complete.

  • 3

    Planning & Regulations

    Keystone can help you move from dreams and aspirations in the design phase to plans on paper. Not all building projects require local authority approval, however building regulations will need to be adhered to and we will ensure compliance with central and local government building controls.

  • 4

    Build

    Typical steps in the build phase of a project are as follows: (Its important to note that timings can vary based on the size and scope of the project)

    Week 1 Set out. Dig out footings. Pour concrete foundations. First delivery of materials.

    Week 2 Build substructure up to damp-proof course. Install/adjust external drainage routes (where appropriate). Install damp-proof course. Pour concrete oversite / floor structure. Erect scaffolding.

    Week 3 Commence construction of exterior walls.

    Week 4 Commence construction of interior walls. Complete construction of exterior walls.

    Week 5 Install roof structure and begin covering. Complete construction of interior walls.

    Week 6 Install windows and doors.

    Week 7 Install/adjust interior drainage (where appropriate). First fix electrics and plumbing. First fix carpentry.

    Week 8 Break through to existing house including installation of steels. Make good all works as a result of breaking through.

    Week 9 Plasterboard and plaster to all areas.

    Week 10 Second fix electrics. Second fix plumbing (where appropriate). Install flooring.

    Week 11 Complete external works – paving, gardening etc. Install skirting. Commence decorating.

    Week 12 Complete decoration. Clean down and remove all waste. Carry out snagging.

  • 5

    Aftercare

    We appreciate that our partnership does not end when the final wall is painted or the last door is hung. We will remain on hand to resolve any issues that arise as a result of the building project and can agree a range of bespoke after care options based on your individual needs.